Licenses library · 706
Factory Operation Certificate
工厂开工证明
ໃບຢັ້ງຢືນດຳເນີນກິດຈະການໂຮງງານ
Those who operate factories Apply at Department of Industry.
Who needs this
Those who operate factories
Requirements
- The factory must meet the condition and standard, be able to produce an experiment then can apply for a Factory Operation Certificate
Documents — first application
| Document | Note |
|---|---|
| List of the machines in the factory | |
| Application Form | by the Industry and Commerce Sector |
| Power of Attorney | |
| Manufacturing Plan | attach with the explanation |
| Annual Operation Plan of the Factory | as defined in the application form by the Industry and Commerce sector |
| Construction Layout | and the technical system of the factory (in A3 paper size) that complies with the construction regulations |
| Photo (3x4) | 4 photos (taken within 3 months) |
| Copy of Enterprise Registration Certificate | Investment License or Business Operating License of Industry and Handicraft |
| Environmental Compliance Certificate (ECC) | (copy) for factories that have impacts on the environment |
| Construction Permit | copy |
| Certificate of Installation of Waste Management System | and/or Waste Disposal Certificate |
| Land Lease Agreement | or Building Lease Agreement or Ownership Certificate of land and Land Title |
| Quality Certificate of Products | for food, drinks, and medicine products |
Legal framework
- Law on Handicraft
- Industrial Processing Law (Amended)
- Presidential Ordinance on Fees and Service Fees
- Devision on Factory
How to submit
- Means of presentation
- At the Authority Offices
- Address of authority
- Department of Industry, Ministry of Industry and Commerce
- Processing time
- 5 - In case the document is incorrect or incomplete the authority must inform the applicant within 5 days from the date of receiving in order to correct it. - If the document is accurate and complete in accordance with the condition and standard, a certificate will be issued within 5 working days.
Validity and renewal
- Has an expiry date
- YES
- Validity
- 36 months
- Renewal process
- The application must be submitted 30 days before the due date
Additional comment
Prior to the permanent production, factory business operators must apply for a factory operation certificate from the industry and handicraft sector first.